PLN Deploys 500 Personel to Restore Power in Flood-Hit Aceh
Jakarta. State utility firm PLN has dispatched 500 personnel from all units across Indonesia to repair the tower sites in the disaster-hit Aceh.
The PLN team also partnered with the Indonesian armed forces.
The personnel checked on the 150-kilovolt high voltage overhead lines (SUTT). About 258 individuals went to the 150-kV SUTT in Arun-Bireuen. PLN deployed 178 personnel at the 150-kV SUTT in Bireuen-Peusangan, and 64 others in P Brandan-Langsa.
"We are very grateful to the TNI for their contribution in strengthening this effort. This collaboration is a crucial factor in the restoration of the damaged transmission network," PLN President Director Darmawan Prasodjo was quoted as saying in a press statement.
PLN has partnered with the Air Force to deliver the logistics, personnel, as well as equipment by air as the disaster had cut off road access.
"Distribution to isolated areas using helicopters is a strategic step to ensure personnel and equipment can reach affected areas quickly," Darmawan said.
The Indonesian Army also helped deploy trucks to reach areas still accessible by land.
"Our personnel are working as hard as possible so we can quickly restore the power system," Darmawan said.
Amiruddin, General Manager of PLN's Main Distribution Unit and Load Regulation Center (UIP3B) for Sumatra, said that personnel and emergency materials had arrived at the affected tower locations.
"Emergency personnel and materials are already at critical points on the affected towers. We are working to ensure the emergency tower construction is completed quickly. This way, we can restore Aceh's power supply as soon as possible," Amiruddin said.
Related Articles
PLN Urged to Prevent Blackouts to Protect Investor Confidence
Recurring blackouts can deter investment in Indonesia, experts say as Suroso leads state utility firm PLN.Prabowo Orders PLN Overhaul, Acceleration of 100 GW Solar Power Plan
Prabowo orders Danantara to review PLN's business model and accelerate a 100 GW solar power plan to improve efficiency and reliability.Power Restored in Eight Batam Areas After Hours-Long Blackout
Power has returned to eight areas of Batam after hours-long blackout disrupted public services, while the cause remains under investigationData Center Power Demand to Reach 25,297 MW by 2034, PLN Says
Indonesia’s data center power demand could reach 25,297 MW by 2034, with 99% of current capacity concentrated in the Java-Bali grid.Indonesia Disburses $18.7 Billion in Energy Subsidies, Compensation
Indonesia disbursed Rp 331.4 trillion in energy subsidies and compensation to PLN and Pertamina as of August, up 52.1% year-on-year.El Nino Cuts South Sulawesi Hydropower Capacity by 600 MW, PLN Says
El Nino has cut hydropower capacity in South Sulawesi by 600 MW, prompting PLN to prepare an additional 627 MW of supply.Let PLN Rent Out the Grid It Already Owns
Indonesia can unlock billions in solar investment by letting companies lease PLN’s grid to buy renewable power directly.Prabowo Targets 30 GW of Solar Power This Year, 100 GW in Four Years
Prabowo targets 100 GW of solar power in four years, a more than 60-fold increase from Indonesia’s current 1.5 GW capacity.Don't Let South Andaman Become Another Masela, Energy Analyst Warns
Indonesia faces calls to swiftly decide South Andaman's gas plan as analysts warn delays could repeat the costly Masela experience.Police Launch $278 Million Coal Supply Corruption Probe Linked to Power Outages
Police have launched an investigation into alleged coal supply corruption blamed for $278 million in state losses and power outages.The Latest
Prabowo Calls Meeting on Forest Fires as Haze Reaches Jakarta, Singapore
Prabowo summons senior officials to discuss forest fires as smoke reaches Jakarta and Malaysia pushes for regional action.Jakarta Outranks Amsterdam in Global Public Transport Survey
Jakarta climbs two places to 15th in Time Out's 2026 public transport survey, with its governor citing better network integration.MSCI Concerns, Tighter IDX Trading Rules Send Indonesian Stocks Down 5% by Midday
Indonesian stocks plunge 5% by midday as MSCI concerns weigh on sentiment and the IDX tightens its daily downside limit to 7%.Jakarta Prepares 367 Health Facilities as Haze Reaches the Capital
Jakarta prepares 367 health facilities to treat potential haze-related illnesses after smoke from Sumatra and Kalimantan crosses the region.Jakarta Expands Flood Prevention With New Water Storage Ponds
Jakarta opens two East Jakarta water storage ponds as it expands flood prevention efforts through reservoirs and river normalization.Most Popular