PTPP’s Kalibaru Terminal Phase 1B Project Reaches 75 Pct in Progress
Jakarta. State-owned construction firm PTPP announced Thursday that its Kalibaru Terminal Phase 1B project in Tanjung Priok Port had reached 75 percent in completion.
The project is worth Rp 3.83 trillion ($233 million). The project aims to strengthen the role of Tanjung Priok Port as the main gateway for export and import distribution in Indonesia. Given its strategic position and connection to various other ports, the development of the port area is a priority to accommodate the increase in cargo and logistics volume and improve loading and unloading services.
In the Kalibaru Terminal Phase 1B Work contract, PTPP is working on a number of strategic work areas, including reclamation and land improvement in the Container Terminal 2 (CT2) area, inner port road, and reserved area. Construction of the 800-meter CT2 pier structure, the 150-meter CT3 pier, dredging of the CT2 pier pool, construction of breakwaters, and the use of innovative technologies such as the vacuum preloading method and LIDAR drones to accelerate implementation and ensure the accuracy of reclamation work.
The vacuum preloading method is a solution to repair very soft soil to ensure structural stability. The use of dredged material as reclamation material is part of PTPP’s efforts to adopt sustainable construction. PTPP also uses BIM (building information modeling) technology and drone LIDAR for precise topography and reclamation volume measurements.
PTPP uses slag cement, a waste product from steel processing, in the deep soil mixing method as part of green construction. This project also uses a 2-meter diameter steel pile that spans 50 meters. This makes it the largest and longest pile in Indonesia and does not have any linkage from Cilegon to Priok.
Pelabuhan Indonesia’s president director Arif Suhartono appreciated the work on the Kalibaru terminal project.
"The quality of the work is neat and good. This is important to keep up with the determined timeline and quality," Arif said.
Arif said that he was optimistic that PTPP could finish the project on time, provide great benefits to the community, and increase the competitiveness of Tanjung Priok Port in the international arena.
This project also has a number of unique features that make it one of the largest modern port developments in Indonesia.
PTPP Corporate Secretary Joko Raharjo revealed that the reclamation activities in this project utilize dredged mud material to form a new area of 260 hectares.
"As well as land improvement in an area of 100 hectares using the vacuum preloading method," Joko said.
Tags: Keywords:Related Articles
PTPP Signs Master Restructuring Agreement to Strengthen Financial Fundamentals
PTPP signs a Master Restructuring Agreement as part of efforts to strengthen its financial structure, liquidity and long-term growth.The Latest
Chandra Asri Group Receives Trade Finance Excellence Award, Reinforcing Its Role in Indonesia’s Industrial Development
Chandra Asri Group receives the Trade Finance Excellence Award at CIMB Niaga Business Summit 2026.AEON MALL Deltamas Brings 11 Sports and Creative Competitions to AEONLYMPIC 2026
AEON MALL Deltamas hosts AEONLYMPIC 2026, featuring 11 sports and creative competitions, with more than 3,100 participants.Indonesian Stocks Extend Losses for Third Day, Fall 3.64% to 4,996
Indonesian stocks fell 3.64% on Monday, extending losses for a third straight session amid MSCI concerns and tighter trading limits.Prabowo Calls Meeting on Forest Fires as Haze Reaches Jakarta, Singapore
Prabowo summons senior officials to discuss forest fires as smoke reaches Jakarta and Malaysia pushes for regional action.Jakarta Outranks Amsterdam in Global Public Transport Survey
Jakarta climbs two places to 15th in Time Out's 2026 public transport survey, with its governor citing better network integration.Most Popular