New Nusantara Toll Road Cuts Balikpapan Travel Time to One Hour
Jakarta. State-owned construction company Hutama Karya has completed construction of the 9.3-kilometer Section 3A of the Nusantara Capital City (IKN) toll road, linking Karangjoang to KKT Kariangau. The project is now undergoing a provisional handover process before entering an operational trial phase to strengthen access to Indonesia’s future capital.
The company finished the work ahead of the government’s target of December 2025, according to Hutama Karya Executive Vice President of Corporate Secretary Adjib Al Hakim.
“Section 3A connects directly to the Balikpapan–Samarinda toll road, cutting travel time from Balikpapan to IKN to about one hour. Shorter access will support mobility for residents, government officials, and businesses,” Adjib said in a statement on Tuesday.
The road forms part of a network with the existing Balikpapan–Samarinda toll road, reducing travel time from the current two to three hours. The section includes three lanes with a total width of 16.15 meters, three bridges spanning the winding Wain River with a combined length of 1.1 kilometers, four overpasses, and one underpass. Of the total stretch, 3.97 kilometers are elevated structures and 4.17 kilometers are built at grade.
“This will be the only toll road in Indonesia that crosses a winding river three times while also intersected by passing barges,” Adjib added.
Hutama Karya applied digital-based construction methods --such as drone mapping, 3D–5D design, and GPS paving-- to improve efficiency and quality. The project has earned ISO certifications in quality, environment, occupational safety, and road safety.
During construction, the company also adopted environmental, social, and governance (ESG) principles, including planting 25,000 mangroves, reinforcing slopes with vegetation, and stabilizing road shoulders with elephant grass. The project created hundreds of jobs, many of which went to local communities, and engaged dozens of small and medium-sized enterprises (SMEs) in the supply chain.
“Local businesses benefited directly from this project, which helped stimulate the surrounding economy,” Adjib said.
The toll road was built in collaboration with a consortium of Hutama Karya, Adhi Karya, and Brantas Abipraya. The company recorded zero accidents and fatalities during construction.
Following the provisional handover, Section 3A will enter a 720-day maintenance period to ensure safety and performance. The toll road will only open for full public use once the entire IKN toll road network—spanning Sections 1A through 6C—is completed, which is projected by 2028.
“Hutama Karya is ready to carry out its government assignment to accelerate connectivity to IKN and spur regional economic growth,” Adjib said.
Tags: Keywords:Related Articles
Vice President Gibran to Begin Working From Nusantara This Year
Vice President Gibran Rakabuming Raka is expected to begin working from Nusantara’s new vice presidential palace later this year.Lion Air Group to Build 30-Hectare Aircraft Maintenance Hub at Future Capital Nusantara
Lion Air Group plans a 30-hectare aircraft maintenance facility at IKN airport as Indonesia prepares to develop it into a commercial hub.Indonesian Parliament Approves $334 Million for New Capital Nusantara in 2027
Indonesia approves Rp6 trillion ($334 million) for Nusantara in 2027, keeping construction on track despite a lower-than-requested budget.Constitutional Court Confirms Jakarta Still Indonesia's Capital, Not Nusantara
Indonesia’s Constitutional Court ruled Jakarta remains the nation’s capital until a presidential decree transfers it to Nusantara.The Latest
Prabowo Calls Meeting on Forest Fires as Haze Reaches Jakarta, Singapore
Prabowo summons senior officials to discuss forest fires as smoke reaches Jakarta and Malaysia pushes for regional action.Jakarta Outranks Amsterdam in Global Public Transport Survey
Jakarta climbs two places to 15th in Time Out's 2026 public transport survey, with its governor citing better network integration.MSCI Concerns, Tighter IDX Trading Rules Send Indonesian Stocks Down 5% by Midday
Indonesian stocks plunge 5% by midday as MSCI concerns weigh on sentiment and the IDX tightens its daily downside limit to 7%.Jakarta Prepares 367 Health Facilities as Haze Reaches the Capital
Jakarta prepares 367 health facilities to treat potential haze-related illnesses after smoke from Sumatra and Kalimantan crosses the region.Jakarta Expands Flood Prevention With New Water Storage Ponds
Jakarta opens two East Jakarta water storage ponds as it expands flood prevention efforts through reservoirs and river normalization.Most Popular